Cheshme khosh production unit development, EPC

Client Ministry of petroleum Iranian central oil fields co.
Project Cheshme khosh utilization unit development
Location Dehloran
Contract Period 20 months

Project objectives

Cheshme khosh utilization unit development to 35000 barrels in a day is the object of this project, with an EPC contract.
In this project a new row is added to 3 existing rows in this unit that based on separating in 3 steps and an experimental separator also, optimizing of control and instruments systems and piping of new row and controlled integrating coordination of cheshme khosh utilization unit is responsibility of BSS.
This project has prophesied on 1387/9.

Joint venture's assignment

The EPC Contract for Ahwaz Bangestan two phase pumping station consisting of endorsement of the Basic Engineering, Detail Engineering, planning, procurement, prefabrication, supply transportation, installations, completion, test and commissioning has been awarded to Joint Venture of BSS / Ramshir and Energy va Sanate.

Project's components

To achieve the object, this project applies: these technical activities:

  • Construction and installation of two 3phases separator.
  • Construction of 2 utilization and degassing tanks.
  • Procurement and installation of new transmit oil pump with 365 m/h capacity and 800m, head.
  • Procurement and installation of control system.