Image Gallery
More images

Shahid mofatteh power plant, Cooling system modification, EPC

Client Ministry of energy
Iranian power Development Company
Project Shahid mofatteh power plant, Cooling system modification, EPC
Location Hamedan
Contract Period 22 months

Shahid mofatteh thermal power plant cooling system is wet type, now the system needs amount of water for cooling the steam production, due to drought in recent years, harvesting ground water and its level drop, .we can observe land subsided. this problem in addition to cooling system water supply , causes to dangers for utilization units of power plant.

Project objectives

The objective of this project is changing the wet into hybrid system to solve the problem of water supply. this project is the first one in it's type and behin saman sarzamin/Tosee Silooha JV has the responsibility of it's engineering, procurement and construction .the dry tower of this project, due to it's steel structure is one of the first steel towers in the country; too.

:Project components

Engineering, procurement, construction and installation of these items are in the responsibility of joint venture:

  • Steel dry tower ,height=133m,bottom diameter=100 m ,gorge diameter=68m
  • Existing condenser modification
  • Heat exchangers
  • Piping
  • Auxiliary cooling tower
  • Cw pump;17000m3/h
  • Copyright ©2011-2012 Behin Saman Sarzamin (BSS), All Rights Reserved
    Design & Programming by IT Department
    copyright