Shirvan combined cycle power plant, fuel storage tanks, EPC

Client Ministry of energy
Iranian power Development Company
Project Shirvan combined cycle power plant, fuel storage tanks; EPC
Location Shirvan
Contract Period 24 months

Project objectives

construction of three 30,000 m³ steel tanks for storage gasoil fuel in Shirvan combined cycle power plant and connect them to existing tanks in power plant, is the aim of this project.

:Project components

engineering, procurement, construction and installation of following items are behin saman sarzamin's missions:

  • Three steel tanks with 30,000 m³ capacity.
  • Boiler room consists of two boilers with 6000 m³/hr and complete accessories.
  • Forwarding pump house with deby 160 m³/hr
  • Forwarding pump house with deby 880 m³/hr
  • Fire fighting foam house
  • Fire fighting concrete water tank with 2300 m³ capacity.