Hormozgan power plant, fuel supply system, EPC

Client Ministry of Energy
Iran power plant projects management Co. (MAPNA)
Project Hormozgan power plant, fuel supply system.
Location Bandar Abbas
Contract Period 9.5 months

Project objectives

This EPC project which is being implemented by the joint venture of BSS and Norahan, is the engineering, procurement and construction of the gas supply system as the main fuel and gas-oil supply system as the substitute fuel system.

Project main components:

A: Gas supply system (Main fuel)

The gas supply system starts from NIGC station via 2,16" gas line to 6 Alstom gas turbines. The gas supply pipeline system is also laid to pressure reducing station and then supplying the gas to the Management building and also to the administration building.

B: The Gas-oil supply system (substitute)

The Gas-oil supply system starts from the Gas-oil depot point with the capacity of 6 trucks discharge at the same time and consists of discharge pump house, 150 m3 storage tank, 2 storage tanks each of 20,000 m3 fuel capacities and the discharge pump house to the different power station units and the relevant pipeline system.

Assignment of the joint venture

Implementation of engineering services, procurement and supply of local and imported equipment installation of pipes, valves measuring facilities, orderings, and all other equipment and facilities required (EPC).